Non-compliance with environmental laws as reported in the National Environmental Compliance and Enforcement Reports
PPC has eleven facilities at the following locations:
- Hercules Cement Factory, Pretoria, Gauteng
- Jupiter Cement Factory, Johannesburg, Gauteng
- Port Elizabeth Cement Factory, Port Elizabeth, Eastern Cape
- Dwaalboom Cement Factory, Dwaalboom, Limpopo
- Slurry Cement Factory, Slurry, North West Province
- De Hoek Cement Factory, De Hoek, Western Cape
- Riebeeck Cement Factory, Riebeeck West, Western Cape
- Saldanha Milling Depot, Saldanha, Western Cape
- Lime Acres Lime Plant, Lime Acres, Northern Cape
- Laezonia Quarry, Gauteng
- Mooiplaas Quarry, Pretoria, Gauteng
Department of Environmental Affairs’ compliance monitoring and enforcement action
Riebeeck West | ||
---|---|---|
NECER | Significant Inspection Findings | Further Developments and Status of Enforcement Process |
20091 | Following an inspection on the 27th of May 2008, a number of findings were made:
|
The following information was also provided in the 2009 report:
|
20102 | The 2010 report provided the following update:
|
|
20113 | As outlined in the 2011 report, representations in relation to the 2008 findings were received in October 2008 and a follow-up inspection was undertaken on the 3rd of December 2009.The principle findings were as follows:
|
The following information was also provided:
|
2012 | – | – |
2013 | – | – |
2014 | – | – |
2015 | – | – |
Port Elizabeth | ||
---|---|---|
NECER | Significant Inspection Findings | Further Developments and Status of Enforcement Process |
20094 | An inspection held on the 27th of May 2008 made the following findings:
|
The status of the enforcement process was reported to be as follows:
|
20105 | In the 2010 report, the following update is provided:
|
|
20116 | As reported in the 2011 report, representations were received on the 22nd of December 2008 and a follow up inspection was undertaken on the 5th of October 2009. The principle findings were as follows:
|
Further information was provided regarding the enforcement strategy:
|
2012 | – | – |
2013 | – | – |
2014 | – | – |
2015 | – | – |
De Hoek | ||
---|---|---|
NECER | Significant Inspection Findings | Further Developments and Status of Enforcement Process |
20097 | In the 2009 report it was recorded that:
According to the 2011 report, these non-compliance findings were made following an inspection in July 2008. |
The following was also reported in the 2009 report:
|
20108 | – | In the 2010 report it was stated that:
|
20119 | Representations had been received on the 9th of December 2008 and a follow-up inspection was undertaken in December 2009. The following are the principle findings made at that inspection:
|
In relation to the enforcement strategy the following information was also provided:
|
2012 | – | – |
2013 | – | – |
2014 | – | – |
2015 | – | – |
Slurry | ||
---|---|---|
NECER | Significant Inspection Findings | Further Developments and Status of Enforcement Process |
200910 | An inspection carried out on the 16th of July 2008 detected 14 non-compliances. It was recorded that alongside dust emission problems the company did not report certain incidents that had the potential to give rise to environmental and health risks to the authorities. | The 2009 report also contained the following statement:
|
201011 | – | The 2010 report provided the following update:
|
201112 | Representations had been received on the 12th of August 2009 and a follow-up inspection had been undertaken on the 13th of May 2010. The following findings were made:
|
The following was stated regarding the enforcement process:
|
2012 | – | – |
2013 | – | – |
2014 | – | – |
2015 | – | – |
Hercules | ||
---|---|---|
NECER | Significant Inspection Findings | Further Developments and Status of Enforcement Process |
200913 | It was recorded that 13 non-compliances had been detected on site, but the date of the inspection was not provided in this or subsequent reports. These non-compliances included the following:
|
In 2009 it was also recorded that:
|
2010 | – | – |
2011 | – | – |
2012 | – | – |
2013 | – | – |
2014 | – | – |
2015 | – | – |
Dwaalboom | ||
---|---|---|
NECER | Significant Inspection Findings | Further Developments and Status of Enforcement Process |
200914 | It was recorded that “all seven non-compliances have been rectified”, but the date of the inspection which found these non-compliances was not provided in this or other years’ reports. | It was also stated that:
The following statement was also made in the 2009 report in relation to each of the PPC operations which featured in the NECERs:
|
201015 | In the 2010 report, the following update is provided:
|
|
2011 | – | – |
2012 | – | – |
2013 | – | – |
2014 | – | – |
2015 | – | – |
201616 | A follow-up inspection was conducted on 1 September 2015. | The report notes that following the inspection conducted on 1 September 2015:
|
- National Environmental Compliance and Enforcement Report 2008/2009, at p28.
- National Environmental Compliance and Enforcement Report 2008/2009, at p27.
- National Environmental Compliance and Enforcement Report 2008/2009, at p54.
- National Environmental Compliance and Enforcement Report 2008/2009, at p28.
- National Environmental Compliance and Enforcement Report 2009/2010, at p27.
- National Environmental Compliance and Enforcement Report 2010/2011, at p54.
- National Environmental Compliance and Enforcement Report 2008/2009, at p29.
- National Environmental Compliance and Enforcement Report 2009/2010, at p27.
- National Environmental Compliance and Enforcement Report 2010/2011, at p55.
- National Environmental Compliance and Enforcement Report 2008/2009, at p29.
- National Environmental Compliance and Enforcement Report 2009/2010, at p27.
- National Environmental Compliance and Enforcement Report 2010/2011, at p55.
- National Environmental Compliance and Enforcement Report 2008/2009, at p29.
- National Environmental Compliance and Enforcement Report 2008/2009, at p28.
- National Environmental Compliance and Enforcement Report 2009/2010, at p27.
- National Environmental Compliance and Enforcement Report 2015/2016, at p60.
- Summary of updated findings
- Summary of findings and company response - 2015
- Company overview
- Non-compliance with environmental laws as reported in the National Environmental Compliance and Enforcement Reports
- Pretoria Portland Cement Company Limited's disclosure of environmental non-compliances in annual reports
- Environmental non-compliances reported by affected communities, the media, & NGOs
- Major shareholders
- Membership of voluntary initiatives, accreditations and awards
- Pretoria Portland Cement Company Limited's response to Full Disclosure